Jing-chun FENG, Ya-fang REN, Zhong-nan DUAN, Zhan-jun LIU, Hai-yang LI. 2012: Penalty model for delay of bidding section construction period in South-to-North Water Diversion Eastern Route Project from perspective of programs. Water Science and Engineering, 5(3): 350-360. doi: 10.3882/j.issn.1674-2370.2012.03.010
Citation: Jing-chun FENG, Ya-fang REN, Zhong-nan DUAN, Zhan-jun LIU, Hai-yang LI. 2012: Penalty model for delay of bidding section construction period in South-to-North Water Diversion Eastern Route Project from perspective of programs. Water Science and Engineering, 5(3): 350-360. doi: 10.3882/j.issn.1674-2370.2012.03.010

Penalty model for delay of bidding section construction period in South-to-North Water Diversion Eastern Route Project from perspective of programs

doi: 10.3882/j.issn.1674-2370.2012.03.010
Funds:  This work was supported by the National Science and Technology Plan of China (Major Project of the Eleventh Five-Year Plan, Grant No. 2006BAB04A13), the Philosophy and Social Science Fund of Education Department of Jiangsu Province (Grant No. 07SJD630006), the Third Key Discipline (Techno-Economics and Management) of the Project 211, and the Key Disciplines of Jiangsu Province (Engineering and Project Management).
More Information
  • Corresponding author: Jing-chun FENG
  • Received Date: 2011-07-14
  • Rev Recd Date: 2012-03-07
  • According to the multi-project and program management theory, this paper analyzes the program generation principle and establishes a program based on progress goals. On the basis of the present situation of calculation of penalty for delay of the bidding section construction period with the critical path method, we studied the effects of contractor-induced delay of the bidding section construction period in detail, including the effects on the construction period of the bidding section itself, the earliest start times of the next bidding section and other subsequent bidding sections, and the construction period of the program, and then constructed a penalty model for delay of the bidding section construction period from the perspective of programs. Using the penalty model, we conducted a practical analysis of penalty for delay of the construction period of the Baoying station program in the South-to-North Water Diversion Project. The model can help determine the amount of penalty for delay of the construction period in bidding sections scientifically and reasonably.

     

  • loading
  • Broome, J., and Perry, J. 2002. How practitioner set share fractions in objectives cost contract. International Journal of Project Management, 20(1), 58-64. [doi: 10.1016/S0263-7863(00)00035-1]
    Browning, T. R. 2001. Applying the design structure matrix to system decomposition and new directions. IEEE Transactions on Engineering Management, 48(3), 292-306.
    Bubshait, A. A. 2003. Incentive/disincentive contracts and its effects on industrial projects. International Journal of Project Management, 21(1), 63-70. [doi: 10.1016/S0263-7863(01)00078-3]
    Federation International Des Ingenieursconseils (FIDIC). 1999. Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer. International Federation of Consulting Engineers.
    Feng, J. C., Hong, Y. Z., Zhang, J., Zhou, Z. B., Sun, W. J., and Wen, S. Y. 2010. Research on the life cycle of the program. Statistics and Decision, (9), 38-40. (in Chinese)
    Feng, J. C., Li, L., Yang, N., Hong, Y. Z., Pang, M., Yao, X., and Wang, L. C. 2011. Research on construction of project critical chain model in South-to-North Water Diversion Project with multi-resource constraints based on portfolio technology. Water Science and Engineering, 4(2), 237-248. [doi:10.3882/ j.issn.1674-2370.2011.02.010]
    He, Z. W., Xu, Y., and Zhu, S. Y. 2005. Study on project payment scheduling problems with bonus-penalty structure from two viewpoints. Systems Engineering—Theory and Practice, 25(10), 39-45. (in Chinese)
    Pillai, A. S., Joshi, A., and Rao, K. S. 2002. Performance measurement of R&D projects in multi-projects concurrent engineering environment. International Journal of Project Management, 20(20), 165-177. [doi: 10.1016/S0263-7863(00)00056-9]
    Reiss, G., Anthony, M., Chapman, J., Leigh, G., Pyne, A., and Rayner, P. 2006. Gower Handbook of Programme Management. Aldershot: Gower Publishing Limited.
    Tareghian, H. R, and Taheri, H. 2006. An application of randomized minimum cut to the project time/cost trade-off problem. Applied Mathematics and Computation, 173(2), 1200-1207. [doi:10.1016/j.amc.2005. 04.063]
    Turner, J., Rodney, J., and Simister, S. J. 2000. Gower Handbook of Project Management. 3rd Ed. Aldershot: Gower Publishing Limited.
    Wang, Y. L., and Yang, Y. H. 2005. Incentive optimization and the determination of optimal project duration to multi-contracts. Forecasting, 24(2), 60-63. (in Chinese)
    Woodbine, G. F. 2004. Moral choice and the declining influence of traditional value orientations within the financial sector of a rapidly developing region of the People’s Republic of China. Journal of Business Ethics, 55(1), 43-60. [doi: 10.1007/s10551-004-5592-5]
    Zheng, W. Y. 2008. A Study on Incentive Mechanism of Construction Project Based on the Theory of Principal-agent. M. E. Dissertation. Tianjing: Tianjing University. (in Chinese)
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Article Metrics

    Article views (2278) PDF downloads(3997) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return